Environmental Remediation – Chicago, IL (North Center)

RW Collins was contracted to perform environmental remediation in accordance with a university campus changing ownership. The campus landscaping had areas of contamination identified during phase 1 assessment. Since most of the buildings and landscape areas were to remain intact, careful planning and operations were needed to ensure the property was disturbed as little as possible, while still completing the remediation objectives.

Contaminants of concern were heavy metals identified in landscape areas throughout the campus. These impacted soils were imported to the site for a landscaping remodeling in the late 1990s. For this project, the client opted for a selective remediation approach. This allowed for a cost-efficient and responsible method of ensuring the health and safety of students and other campus occupants. The selective remediation approach necessitated careful planning and use of equipment. There were significant obstacles in many remediation areas, including underground utilities and campus areas not intended to be disturbed.

 

RW Collins’ skilled equipment operators, laborers, and supervisors ensured minimal disturbance of the existing land. Contaminated soil was carefully removed from parking lot islands, building exterior landscaping, and grass fields. Many of the excavation areas contained utilities that had to remain intact and required careful hand digging.

 

The site’s location in a bustling urban setting required careful planning and traffic control to minimize disturbance to local businesses and residents. Once remediation objectives were complete, landscape restoration for all greenspaces, shrubs, and trees was completed. RW Collins completed all tasks from excavation to finished landscaping on time, within budget, and safely without incident.

Project Facts

  • Three-month project
  • 2-3 crews working simultaneously in different excavation areas
  • Equipment utilized included CAT 328, 315, 308, & 304 excavators, 906 & 938 loaders, 259 & 287 skid steers, vibratory smooth & sheepsfoot drum rollers, remote control operated sheepsfoot roller
  • Over 5,000 tons contaminated soil excavated, hauled & disposed of at subtitle “D” landfill
  • Two underground storage tanks removed
  • Over 12,000 SY of new grass seeding in remediated areas
  • New shrubs, grass, trees, and river rock imported for landscaping restoration
  • Zero disturbance to campus activities
IMG_2566
IMG_2576
IMG_2603
IMG_2746
IMG_2752
IMG_3058
IMG_3113
00F07444-03D3-49A0-89F3-2685AC53F25F
61219673558__CF5C0B6B-AEF5-4731-AB8D-5F320A6F7A37
IMG_2682
IMG_2833
IMG_2895
IMG_2982
IMG_2983
IMG_2566 IMG_2576 IMG_2603 IMG_2746 IMG_2752 IMG_3058 IMG_3113 00F07444-03D3-49A0-89F3-2685AC53F25F 61219673558__CF5C0B6B-AEF5-4731-AB8D-5F320A6F7A37 IMG_2682 IMG_2833 IMG_2895 IMG_2982 IMG_2983