RW Collins was entrusted with the earthwork portion of the project, which involved grading and preparing nearly 100,000 square feet of land. Our crews hauled away more than 7,500 cubic yards of soil, concrete, stone, and asphalt, while also importing and grading over 5,200 cubic yards of stone for the new field base.
Spanning from early April to mid-August, this project highlighted the strength of our fleet and the expertise of our skilled team, delivering a modernized athletic facility that will serve students and neighbors for years to come.
Project Facts
- 100,000 square feet of earthwork completed for field installation.
- Over 7,500 cubic yards of material hauled off-site.
- Over 5,200 cubic yards of stone were installed and graded for the field base.
- 5-man crew: 2 Heavy equipment operators and 3 laborers.
- Equipment: CAT 328, CAT D5, CAT 308, and CAT 265
- Project completed on time, within budget, and safely without incident